An electrical permit in British Columbia is not one price and not one authority. Which fee schedule applies depends on the postal code: Technical Safety BC covers most of the province, but eight local governments run their own electrical permitting, and their brackets are genuinely different from each other. Here is what the 2026 schedules actually say, and where the permit fee belongs in a bid.

Key takeaways
  • Technical Safety BC is the default electrical authority in BC. Eight local governments issue their own electrical permits instead.
  • Fees are driven by the declared value of the electrical work — materials plus labour — not by square footage or device count.
  • The same electrical scope produces a different permit fee in Vancouver than in Burnaby. Check the schedule that governs the site, not the one you used last month.
  • The installation permit, the contractor licence and the annual operating permit are three separate costs with three different holders.
  • If scope grows, the permit has to be amended before final inspection, so the fee moves with your change orders.

Who issues the permit depends on the postal code

Technical Safety BC is the provincial safety authority for electrical work in British Columbia. For most of the province — Langley, Coquitlam, Richmond, New Westminster, Abbotsford, Kelowna, Nanaimo, Prince George — it issues the installation permit and it sends the safety officer.

It is not universal. Technical Safety BC's own jurisdiction page lists the local governments that kept electrical permitting in house:

  • City of Burnaby (electrical and gas)
  • City of Maple Ridge (electrical and gas)
  • City of North Vancouver and District of North Vancouver (electrical and gas)
  • City of Surrey (electrical)
  • City of Vancouver (electrical and gas)
  • City of Victoria (electrical)
  • District of West Vancouver (electrical)

That page also states that in those municipalities Technical Safety BC "typically does not issue permits or perform assessments for electrical or gas work." For a shop based in Cloverdale, that means a job in Surrey, a job in Langley Township and a job in Burnaby run through three different counters with three different fee tables, in the same week. The Surrey market is big enough that plenty of BC shops only ever learn the municipal schedule, then get surprised the first time they bid across the boundary into Langley.

The Technical Safety BC schedule for 2026

Technical Safety BC publishes its rates in an electrical fee schedule with separate 2026 and 2027 columns. Contractor installation permits for general work are banded by the value of the work. At the small end of the 2026 column:

  • Work valued at $150 or less: $15
  • $151 to $400: $36
  • $401 to $1,000: $115
  • $100,001 to $200,000: $3,699

Above $200,001 the schedule switches from flat bands to a base fee plus a percentage of job value. Single-family residential service work is priced differently again — by service size, from $513 for a service of 125 A or less up to $1,706 for a service over 400 A in the 2026 column.

Two costs sit outside the job. A new contractor licence is $267 per unit in 2026 and a renewal is $222. A general-site annual operating permit starts at $296 per site, plus $0.15 per kVA above 300 kVA. Those are business costs, not job costs, and they belong in overhead recovery rather than on a single bid.

Vancouver, Burnaby and Surrey set their own numbers

The municipal schedules are not variations on the provincial one. They are separate instruments with separate brackets, separate minimums and separate annual permits. The figures below come straight from each published schedule, so you can check them against the source rather than against a rule of thumb.

AuthoritySmallest published bandA published mid-range bandAnnual operating permit
Technical Safety BC$15 (work $150 or less)$3,699 ($100,001–$200,000)$296 base plus $0.15/kVA over 300 kVA
City of Vancouver$106 (up to $250)$1,110 plus $43.20 per $1,000 over $10,000$585 up to 500 kVA
City of Burnaby$57.50 ($100 or less)$812 plus $38.50 per $1,000 over $10,000$0.57/kVA, minimum $274, maximum $3,967
City of Surrey$177 ($0–$1,000)$1,728.90 ($34,001–$35,000)published separately by the City

Work an example through it. A $40,000 electrical value in Vancouver lands in the $10,000 to $50,000 band of the City of Vancouver 2026 schedule of development and building permit fees: $1,110 plus $43.20 for each $1,000 above $10,000, which is $2,406. The same $40,000 value in Burnaby lands in that city's $10,000.01 to $50,000 band in the 2026 Burnaby schedule of electrical permit and inspection fees: $812 plus $38.50 per $1,000, or $1,967. Same drawings, same scope, about $440 apart — real money on a job carrying a few thousand dollars of margin.

Surrey publishes its electrical contractor installation permit fee schedule as a tabulated list in $1,000 increments up to $100,000, then switches to formulas: $3,513 plus $18.40 per $1,000 over $100,000 in the $100,001 to $500,000 range, $10,890 plus $10.53 per $1,000 over $500,000, and $16,231 plus $7.17 per $1,000 above $1,000,000. Surrey's minimum is $177, more than triple Burnaby's $57.50 minimum.

Declared value is the number that sets the fee

Every one of these schedules keys off the value of the electrical installation. Burnaby states it plainly: fees are "based on value of electrical installation including materials and labour." That is your electrical portion, not the general contractor's total contract value and not the owner's budget. On a tenant improvement where you are one of six trades, the number you declare is your scope alone.

Under-declaring to save a bracket is a poor trade. Technical Safety BC's installation permit page states that "a permit for the final value and scope of work must be in place before requesting for a final inspection," and that an inspection must occur at least once within 180 days of the permit being issued. If change orders push a job from $38,000 to $62,000, the permit gets amended and the fee follows. The permit line in your estimate is not static — it moves with scope the same way labour does.

Which is why the permit belongs in the takeoff conversation rather than in bookkeeping. If you already build a scope list to price a job, the declared value falls out of it for free. Our takeoff checklist treats it as a line item for exactly that reason.

Where the permit belongs in the estimate

Carry the permit as a direct job cost on its own line, with the authority named beside it. Three reasons. First, if a rival forgot it, you want to point at a line rather than argue about totals. Second, if scope changes, you have a visible number to revise instead of a hidden assumption. Third, the permit is one of the very few inputs on an electrical bid you can source exactly, today, from a published document.

Do not bury it in the material line either. A permit fee is a government charge, not a supply purchase, and it does not behave like material for tax purposes. That is worth reading separately, because the PST treatment of contractor materials in BC is the most common quoting error in the province.

VOLTA carries permit and fee lines as project costs alongside the drafted quantities, so the number rides with the estimate rather than being added by hand at the end. The quantities themselves are drafted from the drawing text and parametric rules across twelve divisions. The contractor still sets the declared value, because only the contractor knows what the final scope is going to be.

Frequently asked

Who issues my electrical permit in BC?
Technical Safety BC issues electrical permits across most of British Columbia. Eight local governments issue their own: Burnaby, Maple Ridge, City and District of North Vancouver, Surrey, Vancouver, Victoria and West Vancouver. Check the jurisdiction of the site, not of your shop.
How much is an electrical permit for a $40,000 job in Vancouver?
Using the City of Vancouver 2026 fee schedule, a $40,000 electrical value falls in the $10,000 to $50,000 band: $1,110 plus $43.20 for each $1,000 above $10,000, which works out to $2,406. Confirm against the current schedule before you quote, because the City updates it annually.
Is the permit fee based on the contract price or just the electrical value?
Just the electrical value. Burnaby's schedule describes it as the value of the electrical installation including materials and labour. On a multi-trade project you declare your own scope, not the general contractor's total contract value.
What happens to the permit fee if the job grows?
The permit has to be amended. Technical Safety BC states that a permit for the final value and scope of work must be in place before a final inspection is requested, so a scope increase means a fee increase. Treat the permit line as something that moves with change orders.
Do I need a contractor licence as well as a permit?
Yes. The licence lets your business do regulated electrical work at all, while the permit covers one specific installation. In the Technical Safety BC 2026 schedule a new contractor licence is $267 per unit and a renewal is $222, which are annual business costs rather than job costs.
Do I need an annual operating permit too?
Only if the site meets the triggers, and that permit is normally held by the building owner or operator rather than the installing contractor. Technical Safety BC's general-site annual operating permit starts at $296 per site with a per-kVA charge above 300 kVA.

Permit fees are the easy part of a bid. The hard part is the twelve hundred lines underneath. VOLTA drafts the takeoff from your PDF in the browser, and you review every quantity before it prices.