An addendum changes the job before you bid it. A change order changes it after you have a contract. Both mean going back into an estimate you thought was finished, and both go badly when the original numbers are hard to find. This post covers what each has to capture and a simple outline to work from. VOLTA does not have a change-order module; the last section says exactly what it can do.

What a change order has to capture

A change order is a small contract. It should let someone who was not on site understand what changed and what it cost:

  • The contract or quote it changes, and a change order number.
  • What changed, and who asked for it.
  • Quantities added and quantities deducted.
  • The labour and material price of the change, with tax.
  • The effect on the schedule.
  • Written approval before the work starts.

Revising a takeoff after addenda

When an addendum arrives during the bid period, read all of it, then mark which electrical sheets and specification sections it touches. Change only the quantities it affects, and note the addendum number beside the changes so you can show what you priced. Most bid forms ask you to acknowledge each addendum; do it, because a bid that ignores one can be rejected.

A simple change order outline

  1. Project, client and original quote reference.
  2. Change order number and date.
  3. Description of the change and the drawing or instruction it comes from.
  4. Added items with quantities and price.
  5. Deducted items with quantities and credit.
  6. Net change, tax, and the revised contract total.
  7. Schedule impact.
  8. Signatures and date.

This is a working outline, not a legal form. Your contract may set its own change procedure, and that procedure governs. There is a shorter version beside the other outlines on the electrical bid template page.

What VOLTA can do today: reopen the file and adjust the numbers

If you came looking for electrical change order software, be clear about what VOLTA is. It is estimating software, and it has no dedicated change-order feature. What it does have is project files you can save and reopen. For an addendum or a change, reopen the estimate, adjust the quantities that changed, and the pricing cockpit re-prices with the same rates, markup and tax as the original. Save the revision as its own file so the original stays intact, and compare the two totals to get the value of the change. The figures are planning estimates; verify quantities and prices before you commit to them.

Start a 30-day free trial

The price line is the same on every page: a 30-day free trial (card required, $0 today), then $9.99 CAD/month plus applicable tax. Every feature is included in the trial, the plan is month-to-month, and you can cancel anytime. Start the 30-day free trial, or read the pricing page first.

Frequently asked

What is the difference between an addendum and a change order?
An addendum changes the bid documents before you submit your price. A change order changes the work after there is a contract.
What should an electrical change order include?
The contract or quote it changes, a description of the change and who asked for it, quantities added and deducted, the price with tax, the effect on the schedule, and written approval before the work starts.
Does VOLTA have a change order feature?
No. VOLTA has no dedicated change-order feature. You can save and reopen a project file, adjust the quantities that changed, and the pricing cockpit re-prices the estimate.
How do I revise an estimate after an addendum?
Read the whole addendum, change only the quantities it affects, note the addendum number beside the changes, and acknowledge the addendum on the bid form.

Keep the original estimate and price the change beside it. Every feature is included in the trial.

Start 30-day free trial

Related: electrical bid template · how to bid electrical jobs · AI takeoff, explained